FY2025 Q2 in brief
Adjusted EPS of $1.25 reflected top-line growth from new rates across Carolinas, Florida, and Indiana, while a $6 billion Brookfield minority stake in Duke Energy Florida and Tennessee LDC sale to Spire at premium valuation were announced.
| Company | Score | Trend | Rev YoY |
|---|---|---|---|
| DUKDuke Energy | 6 | +4.7% | |
| AEEAmeren | 7 | +31.2% | |
| AEPAmerican Electric Power | 8 | +9.9% | |
| CMSCMS Energy | 7 | +14.4% | |
| CNP |
FY2025 Q2 to FY2026 Q3
GAAP revenue YoY +4.68% → base 6. The base score is anchored to the GAAP revenue YoY band before transcript, EPS, and guidance adjustments.
Brookfield Infrastructure investing $6 billion for a minority stake in Duke Energy Florida, enabling FFO-to-debt target increase to 15% and $4 billion incremental Florida capital investment.
Brookfield Infrastructure investing $6 billion for a minority stake in Duke Energy Florida, enabling FFO-to-debt target increase to 15% and $4 billion incremental Florida capital investment.
Sale of Tennessee LDC business to Spire for $2.5 billion or 1.8x rate base, reflecting the high end of LDC asset sale precedents. Proceeds displace common equity needs.
Sale of Tennessee LDC business to Spire for $2.5 billion or 1.8x rate base, reflecting the high end of LDC asset sale precedents.
Amazon Web Services announced plans to invest more than $10 billion to build a new data center campus in North Carolina, expected to create at least 500 new high-skilled jobs.
Amazon Web Services announced plans to invest more than $10 billion to build a new data center campus in North Carolina, expected to create at least 500 new high-skilled jobs.
North Carolina Power Bill Reduction Act allows annual recovery of financing costs for baseload generation. South Carolina Energy Security Act enables rate stabilization mechanism. Ohio approved multiyear rate-making.
North Carolina Power Bill Reduction Act allows annual recovery of financing costs for baseload generation.
Preservation of nuclear production tax credits in final budget reconciliation bill. Duke's 11 gigawatt fleet earned $500 million of PTCs last year for customer benefit.
Preservation of nuclear production tax credits in final budget reconciliation bill.
Long-term FFO-to-debt target raised to 15%, providing 200 basis points of cushion above Moody's downgrade threshold and 300 basis points above S&P.
Long-term FFO-to-debt target raised to 15%, providing 200 basis points of cushion above Moody's downgrade threshold and 300 basis points above S&P.
Rolling 12-month volumes moderated driven by a very strong Q2 2024, particularly in residential. Large customers showing cautious stance amid tariff and policy uncertainty.
Rolling 12-month volumes moderated driven by a very strong Q2 2024, particularly in residential.
AWS committed to a $10 billion data center campus in North Carolina while landmark state legislation was secured in NC, SC, and Ohio.
FFO-to-debt target was raised to 15% from 14% with nuclear production tax credits preserved.
FY25 Q2, sector-relative: EV/Sales 23.8x (79th).
| 4 |
| +2.0% |
| DDominion Energy | 8 | +9.3% |
| DTEDTE Energy | 7 | +18.9% |
| EDConsolidated Edison | 7 | +11.7% |
| EIXEdison International | 5 | +4.8% |
| ESEversource Energy | 7 | +12.0% |
| ETREntergy | 9 | +12.7% |
| EVRGEvergy | 4 | -0.7% | |
| EXCExelon | 5 | +1.2% | |
| FEFirstEnergy | 7 | +3.0% | |
| LNTAlliant Energy | 7 | +7.5% | |
| NEENextEra Energy | 7 | +10.4% |
| Company | Q1 2024 | Q2 2024 | Q3 2024 | Q4 2024 | Q1 2025 | Q2 2025 |
|---|---|---|---|---|---|---|
| DUK | No score | No score | No score | 7 | 7 | 6 |
| AEE | No score | No score | No score | 8 | 8 | 7 |
| AEP | No score | No score | No score | 5 | 7 | 8 |
| CMS | No score | No score | No score | 6 | 8 | 7 |
| CNP | No score | No score | No score | 7 | 6 | 4 |
| D | No score | No score | No score | 4 | 8 | 8 |
| DTE | No score | No score | No score | 5 | 7 | 7 |
| ED | No score | No score | No score | 7 | 7 | 7 |
| EIX | No score | No score | No score | 7 | 4 | 5 |
| ES | No score | No score | No score | 9 | 7 | 7 |
| ETR | No score | No score | No score | 6 | 6 | 9 |
| EVRG | No score | No score | No score | 7 | 7 | 4 |
| EXC | No score | No score | No score | 6 | 8 | 5 |
| FE | No score | No score | No score | 7 | 8 | 7 |
| LNT | No score | No score | No score | 6 | 8 | 7 |
| NEE | No score | No score | No score | 5 | 7 | 7 |
| PCG | No score | No score | No score | 3 | 5 | 4 |
| PEG | No score | No score | No score | 3 | 8 | 9 |
| PNW | No score | No score | No score | 7 | 6 | 5 |
| PPL | No score | No score | No score | 7 | 8 | 6 |
| SO | No score | No score | No score | 6 | 8 | 5 |
| WEC | No score | No score | No score | 7 | 8 | 7 |
| XEL | No score | No score | No score | 3 | 5 | 8 |
Extracted verbatim from public transcripts.
“MVP Southgate will provide 550 million cubic feet per day of capacity from MVP mainline into the Carolinas, serving anchor customers, Duke Energy and the Public Service Company of North Carolina.”
Management on the EQT call · EQT supplies DUK
“This new target will provide 200 basis points of cushion above our Moody's downgrade threshold and 300 basis points above our S&P downgrade threshold.”
Management on the DUK call
Management on the DUK call
“With turbines secured under our framework agreement with GE Vernova and gas supply contracted, we are confident in meeting the in-service time lines we have laid out for these new units.”
Management on the DUK call · DUK buys from GEV
“To highlight a recent project win, Amazon Web Services announced in June that it plans to invest more than $10 billion to build a new data center campus in North Carolina.”
Management on the DUK call · DUK supplies AMZN
“In further support of our capital funding needs, we announced the sale of our Tennessee LDC business to Spire last week. The premium valuation of $2.5 billion or 1.8x rate base reflects the high end of LDC asset sale precedents.”
Management on the DUK call
“Brookfield Infrastructure's $6 billion minority investment in our Florida business. This transaction enables a material strengthening of our credit profile as we enter this period of significant growth as well as the ability to grow our Florida utility at its full potential.”
Percentage of questions scored as challenging, where the analyst pushed back, pressed for specifics, or questioned management's assumptions.
Capital Allocation | Demand | Capex Investment | Regulation Policy | Cloud & AI | Revenue Growth | Guidance Reliability | Innovation & R&D | |
|---|---|---|---|---|---|---|---|---|
| 2024Q4 | 3 | 4 | 1 | 4 | 3 | 4 | 1 | 1 |
| 2025Q1 | 2 | 3 | 2 | 2 | 2 | 1 | 1 | |
| 2025Q2 | 9 | 2 | 4 | 2 | 1 | 1 | 1 | |
| 2025Q3 | 3 | 3 | 5 | 1 | 3 | 1 | 1 | |
| 2025Q4 | 3 | 5 | 2 | 4 | 3 | 2 | 2 | 1 |
| 2026Q1 | 3 | 5 | 2 | 5 | 2 | 1 | ||
| 2026Q2 | 4 | 1 | 7 | 3 | 2 | 1 |
| '24Q4 | '25Q1 | '25Q2 | '25Q3 | '25Q4 | '26Q1 | '26Q2 | |
|---|---|---|---|---|---|---|---|
| Capital Allocation | 3 | 2 | 9 | 3 | 3 | 3 | 4 |
| Demand | 4 | 3 | 2 | 3 | 5 | 5 | 1 |
| Capex Investment | 1 | 2 | 4 | 5 | 2 | 2 | 7 |
| Regulation Policy | 4 | 2 | 2 | 4 | 5 | 3 | |
| Cloud & AI | 3 | 2 | 1 | 1 | 3 | 2 | |
| Revenue Growth | 4 | 1 | 1 | 3 | 2 | ||
| Guidance Reliability | 1 | 1 | 1 | 2 | 2 | ||
| Innovation & R&D | 1 | 1 | 1 | 1 | 1 | 1 |
| PCGPG&E Corporation | 4 | -1.5% |
| PEGPublic Service Enterprise Group | 9 | +15.8% |
| PNWPinnacle West | 5 | +3.8% |
| PPLPPL Corporation | 6 | +7.7% |
| SOSouthern Company | 5 | +7.9% |
| WECWEC Energy Group | 7 | +13.4% |
| XELXcel Energy | 8 | +8.6% |
Management on the DUK call
The table scrolls sideways. Swipe it, or select it and use the arrow keys.
| Quarter | Revenue | Rev YoY | EPS | EPS YoY | Op margin | Net margin | FCF |
|---|---|---|---|---|---|---|---|
| FY2024 Q4 | $7.36B | +2.1% | $1.54 | +21.3% | 28.7% | 16.4% | $288M |
| FY2025 Q1 | $8.25B | +7.5% | $1.76 | +22.2% | 28.4% | 16.7% | -$971M |
| FY2025 Q2Selected | $7.51B | +4.7% | $1.25 | +10.6% | 24.4% | 13.1% | -$417M |
| FY2025 Q3 | $8.54B | +4.8% | $1.81 | +13.1% | 27.3% | 16.6% | $179M |
| FY2025 Q4 | $7.94B | +7.9% | $1.50 | -2.6% | 26.7% | 14.9% | -$485M |
| FY2026 Q1 | $9.18B | +11.3% | $1.97 | +11.9% | 29.7% | 16.9% | -$2.58B |
| FY2026 Q2 | $7.59B | +1.1% | $1.38 | +10.4% | 27.0% | 14.4% | -$1.39B |
| FY2026 Q3 | $9.10B | +6.6% | $1.99 | +9.9% | 30.2% | 17.2% | -$709M |
Management figures may use a non-GAAP, constant-currency, or adjusted basis.
No 8-K events recorded after the FY2025 Q2 call day (Aug 5, 2025) through Nov 7, 2025, inclusive.
| Analyst | Firm | Questions · challenging |
|---|---|---|
| Julien Dumoulin-Smith | Jefferies | 17 questions · 6% challenging |
| Carly Davenport | Goldman Sachs | 14 questions · 0% challenging |
| Nick Campanella | Barclays | 11 questions · 0% challenging |
| Shar Pourreza | Wells Fargo | 8 questions · 13% challenging |
| Jeremy Tonet | JPMorgan | 7 questions · 0% challenging |
| Anthony Crowdell | Mizuho Securities | 6 questions · 0% challenging |
| Steve Fleishman | Wolfe Research | 4 questions · 0% challenging |
| David Arcaro | Morgan Stanley | 4 questions · 0% challenging |
| Durgesh Chopra | Evercore ISI | 4 questions · 25% challenging |
| Alexander Calvert | Wells Fargo | 4 questions · 0% challenging |
| Firm | Analysts | Questions · challenging |
|---|---|---|
| Jefferies | 2 analysts | 19 questions · 5% challenging |
| Goldman Sachs | 1 analyst | 14 questions · 0% challenging |
| Wells Fargo | 2 analysts | 12 questions · 8% challenging |
| Barclays | 1 analyst | 11 questions · 0% challenging |
| JPMorgan | 2 analysts | 8 questions · 0% challenging |
| Wolfe Research | 2 analysts | 7 questions · 0% challenging |
| Mizuho Securities | 1 analyst | 6 questions · 0% challenging |
| Evercore ISI | 2 analysts | 5 questions · 20% challenging |